Irrigation projects in the first quarter of the budget implementation

nmb bank inside

Irrigation projects start in the first quarter of budget implementation

Kathmandu. In the first quarter of the fiscal year 2083/84, the irrigation projects have made an encouraging start.

Under the Department of Water Resources and Irrigation under the Ministry of Energy, Water Resources and Irrigation, in the first quarter, Rs. 239.3 crores have been spent. Of this, 88 percent has been spent on capital i. e. construction works, said Dinesh Rajauria, Director General of the Department.

According to him, Mahakali Irrigation Project (Kanchanpur) has achieved 97.2 per cent of the quarterly physical target. The project has spent Rs 43.7 crore, which is more than two and a half times the quarterly budget. Director General Rajauria said that the Babai Irrigation Project has achieved 81 per cent physical progress against the quarterly target. Sikta Irrigation Project has achieved 80.2 per cent and Rani Jamara Kulariya Irrigation Project has achieved 71 per cent physical progress.

“These four big projects alone have spent Rs 139 crore, which is 58 per cent of the department’s total expenditure,” he said.

According to the department, Praganna-Badkapath (Dang) has made 88.2 percent progress. The deep tube well irrigation project and the Irrigation Institutional Development Programme have achieved 100 percent of the target.

“Both the budget and the work on the projects that have been prepared have progressed. Our priority will be to bring the projects that started late in the second quarter at the same pace.” Director General Rajauria said.